Context notes on energy in Guyana.

Guyana’s offshore capacity passes one million barrels a day.

Gas-to-Energy: gas from offshore for power on land.

Local content: the 2021 Act.

Want to discuss an opportunity in Guyana?

Insights

Short notes on public developments that shape the energy sector where we work. Each one is dated and every figure carries its source.

These notes summarize public information for context. Arahta Energy is not a party to the projects mentioned, and nothing here is investment advice or a forecast.

On 16 November 2026, ExxonMobil started production at Uaru, the fifth development in Guyana’s offshore Stabroek block. Its floating production vessel, Errea Wittu, joins the Destiny, Unity, Prosperity and ONE GUYANA vessels already producing there.

The start-up raises Guyana’s installed production capacity to about 1.1 million barrels a day. Errea Wittu has capacity for 250,000 barrels a day and is expected to reach that rate in the first quarter of 2027.

Source: ExxonMobil, news release, 16 November 2026 .

The Wales Gas-to-Energy project is designed to bring natural gas from Guyana’s offshore fields to a 300 MW power plant and a natural gas liquids facility at Wales, on the West Bank of the Demerara, together with new transmission lines, substations and a national control center.

In May 2026 the Government of Guyana said the contractor was committed to bringing the first power turbine online by the end of 2026, with all gas turbines commissioned by the first quarter of 2027 and combined-cycle operation completed by June 2027.

Sources: Department of Public Information, Government of Guyana, 14 May 2026 ; Fueled, 17 August 2026 .

Guyana’s Local Content Act was signed into law on 31 December 2021. It sets minimum levels of Guyanese participation in the petroleum sector across 40 categories of goods and services, from catering and transportation to insurance and legal services.

A Local Content Secretariat oversees the Act and keeps a register of Guyanese suppliers.

Sources: Office of the President, Government of Guyana ; OilNOW .

FPSO vessels at work in the Stabroek Block, offshore Guyana Home ExxonMobil, news release, 16 November 2026 Department of Public Information, Government of Guyana, 14 May 2026 Fueled, 17 August 2026 Office of the President, Government of Guyana OilNOW Contact us Previous Opportunities